Oracle Primavera Unifier Installation on Windows 

 

Primavera_Unifier_Installation Oracle Primavera Unifier Installation on Windows

 

In this section, I have detailed Oracle Primavera Unifier installation 16.2 on Oracle database on Windows machine.  

 

Follow all the pre-requisites before beginning the Primavera Unifier Installation.  I highlighted the important point in the RED color text. 

 

1. Pre-Requisites

1.1) Follow the link for instruction to download and install Oracle database 12C, make sure to refer STEP 9 in that link. Unifier supports only UTF8 character set.

Oracle Database Enterprise Edition 12C

 

1.2) Follow the link for instruction to Install WebLogic. This link walks through about installation of WebLogic 12.2.1 but makes sure to DOWNLOAD 12.1.3 version instead of 12.2.1. 

WebLogic 12.1.3 Installation

 

1.3) Follow the link for instruction to install ADF Runtime 12.1.3

ADF Runtime 12.1.3 Installation

 

1.4) Follow the link for instruction to create a WebLogic domain for Unifier with OPSS Security. Unifier Restful web service requires OPSS Security

Unifier domain creation with OPSS Security

 

2. Download Primavera Unifier

 

2.1) Log in to http://edelivery.oracle.com

 

2.2) Search for Primavera Unifier. select Platform as Windows, click Continue, continue again

 

053017_0356_OraclePrima1 Oracle Primavera Unifier Installation on Windows

 

2.3) Download Primavera Unifier and Primavera Unifier Project Controls, Facilities and Real Estate Management

 

053017_0356_OraclePrima2 Oracle Primavera Unifier Installation on Windows

 

2.3) Unzip the Unifier zip file in a folder. The folder name starts with Primavera Unifier

 

053017_0356_OraclePrima3 Oracle Primavera Unifier Installation on Windows

 

 

3. Configure WebLogic domain to support Primavera Unifier Rest service (Optional)

 

You can completely ignore this section, that is  step 3.1 to 3.32 if you are not going to use  Primavera Unifier restful web service 

 

3.1) Log into your WebLogic admin console. The URL is http://localhost:7001/console. Click on the Security Realm, myrealm

 

053017_0356_OraclePrima4 Oracle Primavera Unifier Installation on Windows

 

3.2) Click on Roles under Roles and Policies

 

053017_0356_OraclePrima5 Oracle Primavera Unifier Installation on Windows

 

3.3) Click on the button New

 

053017_0356_OraclePrima6 Oracle Primavera Unifier Installation on Windows

 

3.4) Input a Role name UnifierWSAdmin & click Ok

 

053017_0356_OraclePrima7 Oracle Primavera Unifier Installation on Windows

 

3.5) Click on the newly created Role

 

053017_0356_OraclePrima8 Oracle Primavera Unifier Installation on Windows

 

3.6) Click on the button Add Condition

 

053017_0356_OraclePrima9 Oracle Primavera Unifier Installation on Windows

 

3.7) Click Group and Click Next

 

053017_0356_OraclePrima10 Oracle Primavera Unifier Installation on Windows

 

3.8) Input Group name UnifierWSAdmin, Click Add and Finish

 

053017_0356_OraclePrima11 Oracle Primavera Unifier Installation on Windows

 

3.9) Click on the Security Realm and MyRealm again

 

053017_0356_OraclePrima12 Oracle Primavera Unifier Installation on Windows

 

3.10) Click on the User and Groups, Groups tab and click on the button New

 

053017_0356_OraclePrima13 Oracle Primavera Unifier Installation on Windows

 

3.11) Input the Group name UnifierWSAdmin and click Ok

 

053017_0356_OraclePrima14 Oracle Primavera Unifier Installation on Windows

 

3.11) Click on the Users tab and click New

 

053017_0356_OraclePrima15 Oracle Primavera Unifier Installation on Windows

 

3.12) Input a username and password and click Ok

 

053017_0356_OraclePrima16 Oracle Primavera Unifier Installation on Windows

 

3.13) Click on the User

 

053017_0356_OraclePrima17 Oracle Primavera Unifier Installation on Windows

 

3.14) Select the Groups tab, Move the UnifierWSAdmin from left to right

 

053017_0356_OraclePrima18 Oracle Primavera Unifier Installation on Windows

 

3.15) Log in to WebLogic Enterprise Manager with your WebLogic username and password; that is http://localhost:7001/em ; Expand the WebLogic domain and select your domain, Select WSM Policy Sets as shown below

 

053017_0356_OraclePrima19 Oracle Primavera Unifier Installation on Windows

 

3.16) Click on the Create button

 

053017_0356_OraclePrima20 Oracle Primavera Unifier Installation on Windows

 

3.17) Enter the following details and click Next

Name: Unifier_REST_API_Service

Enabled: True

Type of Resource: Restful Resource

Description: Default policy for Unifier REST API service

 

053017_0356_OraclePrima21 Oracle Primavera Unifier Installation on Windows

 

3.18) Enter the following Info & Click Next

 

RESTful Application, Service, or Web Service Endpoint Name: UnfierRestService

 

053017_0356_OraclePrima22 Oracle Primavera Unifier Installation on Windows

 

3.20) Click Next on the Enter Constrains page

 

053017_0356_OraclePrima23 Oracle Primavera Unifier Installation on Windows

 

3.21) Select oracle/wss_http_token_service_policy in the bottom grid and select Attach. It will appear in the Attached Policies . Click Next

 

053017_0356_OraclePrima24 Oracle Primavera Unifier Installation on Windows

 

3.22) Click on the button Save

 

053017_0356_OraclePrima25 Oracle Primavera Unifier Installation on Windows

 

4. Create Primavera Unifier Database Schema

 

4.1) Log in to the Oracle database SYSTEM user account and issue the following queries

 

 

 

5. Configure Primavera Unifier startup script as Windows Service

 

5.1) Go to the unzipped unifier folder (Step 2.3) & Edit the setenv.bat in a notepad file

 

053017_0356_OraclePrima26 Oracle Primavera Unifier Installation on Windows

 

5.2) Add the following three properties. Make sure those values point to your file directory

 

WL_HOME= <MW_HOME>\wlserver\server

JAVA_HOME=<JDK_HOME>

DOMAIN_HOME=<MW_HOME>\user_projects\domains\<DOMAIN_NAME>

ADMINURL = WebLogic Adminserver URL

 

053017_0356_OraclePrima27 Oracle Primavera Unifier Installation on Windows

 

5.3) Open a command prompt as Administrator

 

053017_0356_OraclePrima28 Oracle Primavera Unifier Installation on Windows

 

5.4) Go to the unzipped unifier folder and run the file service.bat

 

053017_0356_OraclePrima29 Oracle Primavera Unifier Installation on Windows

 

5.5) The Command outputs like below

 

053017_0356_OraclePrima30 Oracle Primavera Unifier Installation on Windows

 

5.6) A Windows service got created for Unifier as like in the image below, you can start/stop and restart the Unifier in the Windows services. By default, the startup type mentioned here is Automatic, so the Unifier starts whenever the server starts.

 

053017_0356_OraclePrima31 Oracle Primavera Unifier Installation on Windows

 

5.7) Alternatively, you can start/stop and uninstall the Unifier service using the below command

 

  • service.bat start => Start the Unifier
  • service.bat stop => Stop the Unifier
  • service.bat uninstall => Uninstall the Unifier service

 

6. Configure WebLogic Mobile Setup (Optional)

 

You can skip this part if you are not going to use the Unifier Mobile App

 

6.1) Open the Config.xml file in a notepad that present under MW_HOME\user_projects\domains\unifier\config directory

 

053017_0356_OraclePrima32 Oracle Primavera Unifier Installation on Windows

 

6.2) Add the following tag directly under the <security-configuration>

 

 

 

053017_0356_OraclePrima33 Oracle Primavera Unifier Installation on Windows

 

7. Configure Primavera Unifier

 

7.1) Go to the Unifier unzipped folder (Step 2.3) and go into WebLogic folder. Double click on the configure.bat file

 

053017_0356_OraclePrima34 Oracle Primavera Unifier Installation on Windows

 

7.2) Input the following mandatory fields

 

Server Type: Staging

Temporary Directory: A temp directory

Server Internal URL: Your WebLogic Admin server URL (http://127.0.0.1:7001)

 

Note: The UI will not accept LOCALHOST, Either user the Fully qualified domain name or the IP address

 

053017_0356_OraclePrima35 Oracle Primavera Unifier Installation on Windows

 

7.3) You can select various other options supported. I have selected file system and empty input directories in each field 

Note: Make sure you have created empty directories created before entering each field

 

053017_0356_OraclePrima36 Oracle Primavera Unifier Installation on Windows

 

7.4) Input the Oracle database schema details that you have created In STEP 4.1 and ensure the database connection
is successful

 

053017_0356_OraclePrima37 Oracle Primavera Unifier Installation on Windows

 

7.5) Input your EMAIL server details; Enter dummy text if you don’t have Email server setup already

 

053017_0356_OraclePrima38 Oracle Primavera Unifier Installation on Windows

 

7.6) Input the Markup server or Skip it

 

053017_0356_OraclePrima39 Oracle Primavera Unifier Installation on Windows

 

7.7) Input your BI Publisher details or Skip it

 

053017_0356_OraclePrima40 Oracle Primavera Unifier Installation on Windows

 

7.8) Input your Geo Map details OR Oracle GEO Map or Skip it

 

Map Server Url: https://elocation.oracle.com

Map Tile: elocation.world_map

Map Geocoder Url: https://elocation.oracle.com

 

 

 

053017_0356_OraclePrima41 Oracle Primavera Unifier Installation on Windows

 

7.9) Click on the Authentication tab and input your WebLogic Admin Server details

 

053017_0356_OraclePrima42 Oracle Primavera Unifier Installation on Windows

 

7.10) Click on the Save button & Click Ok

 

053017_0356_OraclePrima43 Oracle Primavera Unifier Installation on Windows

 

7.11) Click on the button Create EAR. This will create an enterprise archive file in the same directory

 

053017_0356_OraclePrima44 Oracle Primavera Unifier Installation on Windows

 

7.12) Wait till the following pop-up comes. Click Ok and Click Close to exit the wizard

 

053017_0356_OraclePrima45 Oracle Primavera Unifier Installation on Windows

 

7.13) The unifier.ear file will get created under the same directory where you run the configure.bat file

 

053017_0356_OraclePrima46 Oracle Primavera Unifier Installation on Windows

 

8. Deploy the Primavera Unifier on WebLogic

 

8.1) Open a command prompt, Go to the Unifier unzipped directory (Step 2.3) . Run the deploy.bat file and enter your WebLogic username and password. You will get the COMPLETED message at the end of the command prompt

 

Note:

  • Make sure your WebLogic admin server is ruining,
  • Make sure you edit the setEnv.bat file as mentioned in STEP 5.2

 

053017_0356_OraclePrima47 Oracle Primavera Unifier Installation on Windows

 

8.2) Log in to WebLogic admin console; Click on the Deployments; You will see a deployment unifier in Active mode

Note: Click on the Name column to make the order descending

 

053017_0356_OraclePrima48 Oracle Primavera Unifier Installation on Windows

 

9 Launch Primavera Unifier

 

9.1) Open a browser and go to  Primavera Unifier Login URL, that is http://localhost:7001/bluedoor

Username: Administrator

Password: Administrator

 

053017_0356_OraclePrima49 Oracle Primavera Unifier Installation on Windows

 

9.2) Reset the password and click Ok

 

053017_0356_OraclePrima50 Oracle Primavera Unifier Installation on Windows

 

9.3) Log in with your reset password account. Below is the default Unifier home page

 

053017_0356_OraclePrima51 Oracle Primavera Unifier Installation on Windows

 

10. Upload Primavera Unifier Project Controls, Primavera Facilities and Real Estate Management

 

10.1) Click on the Applications, Click Install, Update the downloaded Project control zip file (Step 2.3, second zip file ) , Toggle on the check boxes, Fill the details and input password for coadmin . Click on the button Install and click Yes

 

053017_0356_OraclePrima52 Oracle Primavera Unifier Installation on Windows

 

10.2) Wait till the pop-up to finish

 

053017_0356_OraclePrima53 Oracle Primavera Unifier Installation on Windows

 

10.3) Logout and log in as coadmin . Use the password that you mentioned in STEP 10.1

 

053017_0356_OraclePrima54 Oracle Primavera Unifier Installation on Windows

 

10.4) You will see the other unifier settings under Company Works . That’s it.

 

053017_0356_OraclePrima55 Oracle Primavera Unifier Installation on Windows

 

That’s all about Primavera Unifier Installation. Please feel free to share your comments below. J

 

govindan Oracle Primavera Unifier Installation on Windows
Connect me

Govind

Thank you for visiting my personal blog. Myself Govindan, Software Developer by profession since 2006 and hence I started this blog early in 2016 and ever since I've been writing about technologies experienced and learnings of everyday life.

The views expressed on this blog are my personal views and do not necessarily reflect the views of my employer.

Please feeling free to reach me on any comments and feedbacks you have. Would be more than glad to listen and reply 🙂
govindan Oracle Primavera Unifier Installation on Windows