Primavera P6 calculating Finish Date at 8 AM if it has FF relationship with Negative Lag

 

In my projects, the finish date of an activity ends at 8 AM instead of 5 PM. This occurs to activities where LAG has negative days. Here below I have created an example project with the same scenario. As you see in the below image, the finish date of third activity ends at 8 AM even it has a full Planned Duration in it.

The following project has three activities;

  • The Activity ‘1’ successor is ‘2’ and ‘2’ successor is ‘3’
  • The Activity ‘2’ is a Finish Milestone, ‘1’ and ‘3’ are Task Dependent Activities
  • Lag of -1 day is assigned to predecessor of ‘3’ rd activity 
  • Standard 5 Day calendars assigned to all activities; There is no exception in the calendar;
  • Finish Date ends in AM If I Scheduled the project on 24-Jun-17

     

Adding negative day lag will remove the corresponding working hours per day from the date and shows Finish Date in 8AM.

 

103017_0336_PrimaveraP61 Primavera P6 Calculating Finish Date at 8 AM if it has FF relationship with negative Lag

 

 

Download P6 Project XML file : 

 

govindan Primavera P6 Calculating Finish Date at 8 AM if it has FF relationship with negative Lag
Connect me

Govind

Thank you for visiting my personal blog. Myself Govindan, Software Developer by profession since 2006 and hence I started this blog early in 2016 and ever since I've been writing about technologies experienced and learnings of everyday life.

The views expressed on this blog are my personal views and do not necessarily reflect the views of my employer.

Please feeling free to reach me on any comments and feedbacks you have. Would be more than glad to listen and reply šŸ™‚
govindan Primavera P6 Calculating Finish Date at 8 AM if it has FF relationship with negative Lag
Connect me

Latest posts by Govind

By | 2017-10-29T22:49:09+00:00 October 29th, 2017|Categories: P6|Tags: , , |0 Comments
Like us on Facebook.
Connect!