How to set default Planned Duration for new activities in Primavera P6?

 

e add a new activity in Primavera P6 a planned duration of 5 days comes by default as shown below

 

102917_0236_Howtosetdef1 How to set default planned duration for new activities in Primavera P6

 

We can control this feature. That means we can change the default planned duration in Primavera P6 Application setting. To do this:

 

Login to P6 as Admin >> Administer >> Application Settings >> General >> Activity Duration >> Set Default duration for new activities

 

102917_0236_Howtosetdef2 How to set default planned duration for new activities in Primavera P6

 

That’s it. Input a different duration above in the above field and add an activity again. The new duration will reflect in the Planned Duration.

govindan How to set default planned duration for new activities in Primavera P6
Connect me

Govind

Thank you for visiting my personal blog. Myself Govindan, Software Developer by profession since 2006 and hence I started this blog early in 2016 and ever since I've been writing about technologies experienced and learnings of everyday life.

The views expressed on this blog are my personal views and do not necessarily reflect the views of my employer.

Please feeling free to reach me on any comments and feedbacks you have. Would be more than glad to listen and reply šŸ™‚
govindan How to set default planned duration for new activities in Primavera P6
Connect me

Latest posts by Govind

By | 2017-10-28T21:41:42+00:00 October 28th, 2017|Categories: P6|Tags: , , , |0 Comments
Like us on Facebook.
Connect!